Commencement | Completion | Project Name | Scope of the Project | |
---|---|---|---|---|
1995 | 1995 | SEKA DALAMAN FACTORY/ MUĞLA, TURKEY GAS DUCTS RENEWAL |
Within the scope of this project, recovery furnace gas ducts and evaporator gas pipes were fabricated, the old system was demounted and renewed. | |
1995 | 1995 | SEKA DALAMAN FACTORY/ MUĞLA, TURKEY RECOVERY FURNACE LAVA CHUTE RENEWAL |
Within the scope of this project, existing lava chutes were removed from the recovery furnace and the new ones were installed. 100% radiography control was carried out. | |
1994 | 1994 | SEKA DALAMAN FACTORY/ MUĞLA, TURKEY BALING PRESS ERECTION |
Within the scope of this project; the modernization of 50 tons / day hydraulic baling press in the production line of viscose cellulose and fabrication and erection of automatic packaging, labeling and dust collection system were completed. | |
1993 | 1993 | SEKA DALAMAN FACTORY/ MUĞLA, TURKEY INSTALLATION OF HVAC DUCTWORKS IN MCC ROOMS FOR PAPER AND CARDBOARD FACTORIES |
Within the scope of this project, fabrication and installation of air ducts and commisioning of the system were completed. | |
1989 | 1990 | SEKA DALAMAN FACTORY/ MUĞLA, TURKEY RECOVERY FURNACE REPAIR AND MODIFICATION |
Within the scope of this project; demounting and erection of furnace floor and side walls, primary/ secondary boiler, primary/secondary air chambers, modification of solution tank and stack, fan and air heaters erection, gas ducts demounting and erection, erection of soot blowing equipment and piping erection, furnace ceiling renewal, steel construction works, black liquor and fuel oil boiler and piping installation economiser repairment, lava chute and cooling water system erection, isolation and coating works and chemical washing of furnace were completed. | |